項(xiàng)目風(fēng)險(xiǎn)管理-PMP考試章節(jié)練習(xí)(16-20題)16. Decision trees are best used for:
A. determining the interaction of the amount at stake and the expected value
B. association of the probabilities with the risk events
C. an illustration of how to see the interactions between decisions and the associated events
D. a flow chart which determines the standard deviation of the risk event
決策樹(shù)的最佳用途是:
A. 確定風(fēng)險(xiǎn)所帶來(lái)的損失和預(yù)期的風(fēng)險(xiǎn)情況下獲得利潤(rùn)之間的關(guān)系
B. 風(fēng)險(xiǎn)事件之間的概率關(guān)系
C. 一種展示決策和相關(guān)事件之間關(guān)系的圖形化的方法
D. 一種流程圖用來(lái)確定風(fēng)險(xiǎn)事件的標(biāo)準(zhǔn)偏差
17. Contained within the first step of a five step process to determine the risk analysis of the project’s risk events, a process of ________ is performed to see if the risk should be included or excluded as part of the project scope
A. determining the probability
B. contingency effort
C. assessing the consequences and severity
D. screening
在五個(gè)用來(lái)確定項(xiàng)目風(fēng)險(xiǎn)事件的分析過(guò)程的第一步中,__________ 的流程的執(zhí)行是為了確定風(fēng)險(xiǎn)是否包括在項(xiàng)目范圍的一部分中。
A. 確定概率
B. 應(yīng)急投入
C. 評(píng)估結(jié)果和嚴(yán)重度
D. 篩選
18. A project of 2 million has an adverse event that has probability of 50% of occurrence and a potential loss of $20,000. This represents an expected negative value of:
A. $100,000
B. $1,000
C. $100
D. $10,000
一個(gè)兩百萬(wàn)美元的項(xiàng)目有50%的可能會(huì)損失20000 美元。這表示預(yù)期的不利損失是:
A. 100000 美元
B. 1000 美元
C. 100 美元
D. 10000 美元
19. The assigned values of risk for a project is best accomplished through a structured methodology that ensures all project elements are evaluated. The project tool that is best suited for the structured analysis of the project risk is the:
A. contract
B. specification
C. statement of work
D. work breakdown structure
E. network programming diagram
給項(xiàng)目賦予風(fēng)險(xiǎn)值最好是通過(guò)一個(gè)結(jié)構(gòu)化的方法完成,此方法能保證所有的項(xiàng)目元素都進(jìn)行了評(píng)估。最適合這種結(jié)構(gòu)化風(fēng)險(xiǎn)分析的工具是:
A. 合同
B. 規(guī)范
C. 工作說(shuō)明
D. WBS
E. 網(wǎng)絡(luò)計(jì)劃圖
20. The total amount of risk that is calculated for a project is found by:
A. multiplying the sum of each the risks times the amount at stake
B. calculating the cumulative sum of the probability for each risk and multiplying this value times the consequence of occurrence of the risk events
C. cannot be calculated since all risks are not known
D. the amount of project reserves available
項(xiàng)目風(fēng)險(xiǎn)總值的計(jì)算是:
A. 各個(gè)風(fēng)險(xiǎn)的總和乘以其所帶來(lái)的價(jià)值
B. 計(jì)算各個(gè)風(fēng)險(xiǎn)的概率乘以其所帶來(lái)的結(jié)果的價(jià)值的總和
C. 不能計(jì)算出來(lái),因?yàn)樗械娘L(fēng)險(xiǎn)都不知道
D. 項(xiàng)目可用備用金的金額
PMP考試練習(xí)答案(風(fēng)險(xiǎn)管理):16-20 CDDDB