PMP考試每天一練--2016年PMP考試試題及答案解析7
7、A project manager has just been assigned to a new project and has been given the project charter.The FIRST thing the project manager must do is: A.create a project scope statement. B.confirm that all the stakeholders have had input into the scope. C.analyze project risk. D.begin work on a project management plan. 7、項目經理剛剛分配到新項目上,已經完成項目章程。項目經理首先應該做什么? A、創建項目范圍說明書 B、確保所有的干系人有輸入到范圍中 C、分析項目風險 D、開始項目管理計劃上的工作 正確答案:B 試題解答:選項B等于識別干系人。 |