PMP考試每天一練--PMP考試試題-33
PMP考試試題: A functional manager of a project team has refused a request to release a resource to a project; the project manager decides to meet with the functional manager to find a solution. Which skill is the project manager using? A. Compromise B. Conflict management C. Exercising authority D. Negotiation 一個職能經理拒絕安排某個員工到項目上去。項目經理決定與職能經理當面討論,尋求解決方案。項目經理使用的是什么技巧? A. 妥協 B. 沖突管理 C. 行使職權 D. 談判 PMP參考答案:D. 談判 PMP答案解析:組建項目團隊工具-談判 ( 9.2.2.2 )P270 |