PMP考試每天一練--PMP考試試題-50
PMP考試試題一: You are taking over a project during the planning process group and discover that six individuals have signed the project charter. Which of the following should MOST concern you? A. Who will be a member of the change control board B. Spending more time on configuration management C. Getting a single project sponsor D. Determining the reporting structure 項目進入了規劃階段你才接手,并且發現六個人已經簽署了項目章程。以下你最應該關注哪項? A. 變更控制委員會會員是誰。 B. 花更多的時間進行配置管理。 C. 使項目有一個項目發起人。 D. 確定匯報結構。 PMP參考答案:B. 花更多的時間進行配置管理。 PMP答案解析:整體變更控制流程 (4.5)P94 PMP考試試題二: A project manager and team from a firm that designs railroad equipment are tasked to design a machine to load stone onto railroad cars. The design allows for two percent spillage, amounting to over two tons of spilled rock per day. In which of the following does the project manager document quality control, quality assurance, and quality improvements for this project? A. Quality management plan. B. Quality policy. C. Control charts. D. Project management plan. 鐵路設備公司的項目經理和他的團隊接到任務設計一臺機器用來給火車車廂裝載石頭,該設計允許2%的溢漏量,也就是每天累計的溢漏量超過兩噸。那么,項目經理將質量控制、質量保證和過程改進的文檔記錄在: A. 質量管理計劃。 B. 質量政策。 C. 控制圖。 D. 項目管理計劃。 審題: 此題的關鍵字為“。。。質量控制、質量保證和過程改進的文檔記錄在。。。”,講的是制定質量管理計劃的事。 定位: 規劃過程組·質量管理·8.1.3規劃質量管理:輸出 解析: 1、質量管理計劃是規劃質量的輸出。質量管理計劃包括項目的質量控制、質量保證和持續過程改進。 2、B質量政策屬于組織過程資產;C控制圖用來確定一個過程是否穩定或者是否具有可預測的績效,有上下限, 是一種工具與技術;D項目管理計劃范圍相對于“質量控制、質量保證和過程改進的文檔”范圍太廣。 PMP參考答案:A. 質量管理計劃。 |