PMP考試每天一練--PMP考試試題168
PMP考試試題一: The initial cost of your project is $25,000, which will save the company $6,000 year for the next four years. Using the data in the following table, if your company wants a 12% ROI, what is NPV of the project? A. -$1,000 B. -$6,772 C. +$1,758 D. +$6,772 你項目的初始成本是$25,000,這將在以后四年內每年節省公司$6,000。根據以下表格數據,如果利率是12%,那么項目的凈現值是多少?年 10% 12% 1、0.909 0.893 2、0.826 0.797 3、0.751 0.712 4、0.683 0.636 A. -$1,000 B. -$6,772 C. +$1,758 D. +$6,772 PMP答案解析:規劃成本管理工具-分析技術-凈現值(7.1.2.2 ) P198 PMP參考答案:B. -$6,772 PMP考試試題二: What percent of time do project managers spend communicating? A.90. B.20. C.70. D.25. 項目經理用于溝通的時間百分比應該是: A. 90 B. 20 C. 70 D. 25 審題:此題解題的關鍵是找到題干關鍵句“項目經理”和“溝通”。 定位:溝通管理領域的拓展 解析:項目經理應該花費大量的時間在溝通上。請記住這個數字。 項目經理的主要工作是整合管理和溝通管理。 PMP參考答案:A. 90 |