PMP考試每天一練--PMP考試試題176
PMP考試試題一: A seller is awarded a contract to build a pipeline. The contract terms and conditions require that a work plan be issued for the buyer's approval prior to commencing work, but the seller fails to provide one. Which of the following is the BEST thing for the buyer's project manager to do? A. File a letter of intent. B. Develop the work plan and issue it to the seller to move things along. C. Issue a default letter. D. D. Issue a stop work order to the seller until a work plan is prepared. 賣方被授予一個管道建設合同。合同條款規定要在開始工作之前發布工作計劃以取得買方的批準,但是賣方未能提供工作計劃。下列哪項是買方的項目經理最好的做法? A. 記錄意向書 B. 開發工作計劃并向賣方發布 C. 發布違約信 D. 向賣方發布中止工作表,直到編制完工作計劃 PMP答案解析:合同管理 PMP參考答案:C.發布違約信 PMP考試試題二: You are working with a group of managers to decide which projects to pursue. Cost is an important consideration.Whick type of costs should not be a criteria in project selection? A. Indirect costs. B. Sunk costs. C. Tangible costs. D. Intangible costs. 你和一個經理團隊一起決定進行哪一些項目,成本是重要的考慮因素,下面哪一項不是項目選擇的標準? A. 直接成本。 B. 沉沒成本。 C. 有形成本。 D. 無形成本。 審題:此題解題的關鍵是找到題干關鍵句“決定進行”、 “不是” 定位:成本管理的拓展。 解析: 1、有形和無形成本及收益的分類主要是為了確定所估計的項目成本和收益的可確定程度。有形成本(tangible costs)或有形收益(tangible benefits)是能夠容易地用貨幣來衡量的成本或收益。 2、項目的無形收益通常包括與其他企業建立良好關系,樹立威信以及其他一些很難用貨幣來衡量的生產力進步。因為無形成本和收益很難量化,因而它們通常很難加以證明。 3、直接成本(direct costs)是直接與項目的產品和服務的生產相關的成本。你能夠把直接成本直接歸結于某一項目。例如,項目中全職工作人員的薪金、為項目專門購買的硬件和軟件等都是直接成本。項目經理應該重視直接成本,因為它們是可控的。 4、間接成本(indirect costs)是與項目的產品和服務的生產不直接相關的成本,但是它們間接的與項目的績效掛鉤。例如,在一個大的辦公樓里,為許多項目工作的上千員工所使用的電力費用、紙巾等都是間接成本。間接成本是分攤給項目的,因此,項目經理很難控制。 5、沉沒成本(sunk cost)是過去已經花掉的錢,它就像沉船一樣永遠不會回來。當決定投資或繼續投資哪些項目時,應該不考慮沉沒資本。 PMP參考答案:B. 沉沒成本 |