PMP考試每天一練--PMP考試試題192
PMP考試試題一: All project deliverables are completed according to the customer’s expectations. The project manager is assigned to a new project with aggressive timelines.What should the project manager do next? A.archive all project documentation B.complete a financial analysis of the project and communicate any variance to stakeholders C.obtain financial, legal, and administrative closure using generally accepted practices D.move onto the new project immediately 所有項目可交付成果均已按照客戶期望完成。項目經理被分配管理一個工期緊的新項目。項目經理接下來應該怎么做? A.將所有項目文檔存檔 B.完成項目的財務分析,并與干系人溝通任何偏差 C.使用普遍接受的管理獲得財務、法律和行政結尾 D.立即轉到新項目的工作 PMP答案解析:項目已完成,下一步是按照流程進行項目收尾。選項A只是收尾的其中一個步驟,C更全面。 PMP參考答案:C PMP考試試題二: If a project has a 60 percent chance of a U.S. $100,000 profit and a 40 percent chance $100,000 loss, the expected monetary value for the project is: of a U.S. A. $100,000 profit B. $60,000 loss C. $20,000 profit D. $40,000 loss 假設有一項目,其獲利100,000美元的概率為60%,損失100,000美元的概率為40%,那么該項目的預期貨幣價值為: A. 獲利100,000美元 B. 損失60,000美元 C. 獲利20,000美元 D. 損失40,000美元 PMP答案解析:定量風險分析工具-建模和模擬-EMV(11.4.2.2) P338 PMP參考答案:C |