PMP考試每天一練--PMP考試試題196
PMP考試試題一: A project manager begins a new project and wants to learn about a similar project’s successes and failures. However, only the closing documents were archived.What project document should the project manager reference to deliver the new project? A.work breakdown structure B.probability impact matrix C.project charter D.lessons learned 項目經理開始一個新項目,并希望了解類似項目的成功和失敗。但是,只有存檔收尾文檔。項目經理應參閱哪一封項目文件來交付新項目? A.工作分解結構 B.可能性影響矩陣 C.項目章程 D.經驗教訓 PMP答案解析:了解類似項目的成功和失敗,是經驗教訓總結。 PMP參考答案:D.經驗教訓 PMP考試試題二: You are evaluating vendor proposals and using selection criteria in order to choose a vendor. One of the criteria states that resources are required to have civil engineering degrees and a minimum of three years of experience. Which of the following tools and techniques does this question refer to: A. Weighting systems B. Procurement negotiation C. Independent estimate D. Screening systems 你在選擇某種評估標準來評估供應商建議書,其中有一條標準是要求供應商的資源要有民用建筑工程學位,以及至少三年以上經驗。這一評估技術是: A. 加權系統 B. 采購談判 C. 獨立估算 D. 篩選系統 PMP參考答案:D. 篩選系統 |