PMP考試每天一練--PMP考試試題197
PMP考試試題一: The project manager conducts an inspection with the customer to confirm that the project deliverables meet the product acceptance criteria and fulfill thecustomer’s expectations.These actions are part of which of the following processes? A.control quality B.close project or phase C.Control scope D.Validate scope 項目經理與客戶一起進行檢查,確認項目可交付成果是否符合產品驗收標準并滿足客戶的期望。這些行動都屬于下列哪一個過程的組成部分? A.控制質量 B.項目或階段收尾 C.控制范圍 D.核實范圍 PMP答案解析:根據題干PM與客戶是在確認范圍,即核實范圍。 PMP參考答案:D.核實范圍 PMP考試試題二: You are managing a six-month project and have held bi-weekly meetings with your project stakeholders. After five-and-a-half months of work, the project is on schedule and budget, but the stakeholders are not satisfied with the deliverables. Thissituation will delay the project completion by one month. The MOST important process that could have prevented this situation is: A. Monitor and Control Risks. B. Control Schedule. C. Define Scope. D. Control Scope. 你正在管理一個歷時六個月的項目,而且每兩周要和項目干系人召開狀態會議。工作完成五個半月后,項目的進度和預算均在計劃內,但干系人對可交付成果并不滿意。這樣會導致項目延期一個月完工。阻止此類問題發生的最有效的過程是哪個? A.控制風險 B.控制進度 C.定義范圍 D.控制范圍 PMP參考答案:C.定義范圍 |