PMP考試每天一練-2018年PMP考試練習題12
PMP考試練習題一: At a stakeholder meeting, it is identified that the stakeholder group should include a community based organization (CBO). The project manager is concerned that there will be a lack f executive support for the inclusion of the CBO.What should the project manager do first? A. Send the CBO periodic updates B. Initiate perform integrated change control process C. Inform executives that the CBO will be included D. Expand regular project status communications to include the CBO 在干系人會議上,確定干系人團體應包含一個以社區為基礎的組織(CBO)。項目經理擔心包含CBO將缺少執行者的支持。項目經理首先應該做什么? A.向CBO定期發送更新情況 B.開始執行整體變更控制過程 C.通知執行者,將包含CBO D.擴大常規項目狀態溝通范圍,包含CBO PMP答案解析:因為涉及到高管層的意見,建議選B PMP參考答案:B PMP考試練習題二: A team of four sponsors gives a project charter to the project manager. In addition to the project manager, the project team consists of seven members from different functional groups.What is the number of communication channels? A.4 B.21 C.55 D.66 由四名發起人構成的團隊向項目經理提供了一份項目章程。除了項目經理以外,項目團隊由來自不同職能組織的七名成員組成。溝通渠道總數有多少? A.4 B.21 C.55 D.66 PMP答案解析:(4+1+7)*(4+1+7-1)/2=66 PMP參考答案:D |