PMP考試每天一練-2018年PMP考試試題17
PMP考試試題一: A software project is nearing completion when a tester reports a major defect. The developer believes that the solution will require significant rework and affect delivery. The project manager consults the user representative and project sponsor. The former believes that the defect exists only m theory, as it has never occurred before; the latter indicates that the delivery date cannot be changed. Subsequently, the project manager records the defect in the issue log and closes the report. Two weeks later, the developer informs the project manager of a solution that will not affect the schedule, and asks to begin immediate implementation. What should the project manager do next? A. Notify the user representative and project sponsor about the new solution. B. Hold a meeting with the project team to assess the new solution. C. Tell the developer that it has been noted in the issue log, but not to implement it. D. Ask the testing team to evaluate how long testing the solution will take. 一個軟件項目進行到交付前的沖刺階段,測試人員報了一個主要缺陷,而開發人員認為解決方案需要大面積返工并影響交付。項目經理征詢用戶代表和項目發起人的意見,前者認為此缺陷雖理論上存在但沒發生過:后者則表示交付日期不可改動。項目經理最終把該缺陷記錄在問題日志上,并關閉了該缺陷報告。兩周后,開發人員找到項目經理,說有一個更好的解決方案,只要一周就能修改這個主要缺陷且不會影響按時交付,想馬上動手進行修復,這位項目經理應該怎么做? A.與用戶代表及項目發起人溝通新的解決方案。 B .找項目團隊一起開會,來評估該開發人員的修改方案。 C.告訴開發人員已經在問題日志上記錄了,就不修改了。 D.聯系測試組評估修改會帶來的測試工作。 PMP答案解析:B PMP參考答案:缺陷補救屬于變更,需要首先來評估變更影響,B與D都是評估,推薦選 B,B可以包含 C提到的內容。 PMP考試試題二 What is the purpose of a bidder conference when soliciting responses to a request for proposal (RFP)? A. Allows the vendors to provide preliminary conceptual designs B. Ensures prospective vendors have a common understanding of the procurement process C. Allows the buyer to disqualify vendors from the bid process D. Provides a forum for negotiation with prospective vendors 征求建議邀請書(RFP)答復時,投標人會議的目的是什么? A.允許供應商提供初步概念性設計 B.確保潛在供應商對采購過程達成共識 C.允許買方取消供應商參與投標過程的資格 D.提供一個論壇,與潛在供應商談判 PMP答案解析:投標人會議的目的是保證所有潛在賣方對采購要求都有清楚且一致的理解,保證沒有任何投標人會得到特別優待。 PMP參考答案:B |