PMP考試每天一練-2018年PMP考試試題20
PMP考試試題一: A new building project finished, and the project team is awaiting the certificate of occupancy. The team must provide all building documentation. Where is this documentation included? A. Enterprise environmental factors B. Configuration management C. Corporate knowledge base D. Closed procurements 一個新的建筑項目完成后,項目團隊正在等待入住證明,團隊必須提供所有建筑文檔。下面哪一項是這個文檔要包括的? A. 事業環境因素 B. 配置管理 C. 企業知識庫 D. 已收尾的采購 PMP答案解析:本題表述不夠完整,4個參考答案中, BCD都是屬于項目文檔,是題意最相關的推薦為D PMP參考答案:D PMP考試試題二 A new project manager assigned during a project’s execution phase must meet with the project stakeholders. What should the project manager do to determine who the key stakeholders are? A. Review the stakeholder register and the available project date B. Request the project charter C. Refer to the risk register D. Use interviewing techniques 一名在項目執行階段任命的新項目經理必須與項目干系人開會。若要確定哪些干系人是關鍵干系人,項目經理應該怎么做? A.審查干系人登記冊以及可用的項目數據 B.請求項目章程 C.查閱風險登記冊 D.使用訪談技術 PMP答案解析:干系人登記冊是識別干系人過程的主要輸出,用于記錄已識別的干系人的所有詳細信息 PMP參考答案:A |