PMP考試每天一練-2018年P(guān)MP考試試題25
PMP考試試題一: During the early phases of a project, the project manager realizes that the project budget is dependent on the price of raw materials. What should the project manager do next? A.Update the scope statement B.Buy the raw materials before prices increase C.Update the risk register D.Ask for a change request 在項(xiàng)目早期階段,項(xiàng)目經(jīng)理意識(shí)到項(xiàng)目預(yù)算取決于原材料的價(jià)格。項(xiàng)目經(jīng)理接下來(lái)應(yīng)該怎么做? A.更新范圍說(shuō)明書 B.在價(jià)格上漲之前采購(gòu)原材料 C.更新風(fēng)險(xiǎn)登記冊(cè) D.要求變更請(qǐng)求 PMP答案解析:“項(xiàng)目預(yù)算取決于原材料的價(jià)格”說(shuō)明具有一定的不確定性,這是風(fēng)險(xiǎn) PMP參考答案:C PMP考試試題二 The project manager plans to purchase concrete for a building construction project, the quality of the materials is consistent among all vendors, leaving price as the major difference.Which type of vendor response should the project manager request? A.Request for information B.Request for proposal C.Statement of work D.Request for quotation 項(xiàng)目經(jīng)理計(jì)劃為一個(gè)建設(shè)施工項(xiàng)目采購(gòu)混凝土。所有供應(yīng)商的材料質(zhì)量都一樣,只有價(jià)格有主要區(qū)別。項(xiàng)目經(jīng)理應(yīng)向供應(yīng)商請(qǐng)求那種應(yīng)對(duì)類型 A.信息請(qǐng)求 B.建議邀請(qǐng)書 C.工作說(shuō)明書 D.報(bào)價(jià)邀請(qǐng)書 PMP答案解析:題干說(shuō)供應(yīng)商的材料質(zhì)量都一樣,只有價(jià)格有區(qū)別,選報(bào)價(jià)邀請(qǐng)書 PMP參考答案:D |