PMP考試每天一練-2018年PMP考試試題33
PMP考試試題一: Midway through a project's execution phase, a team member proposes changes to provide more flexibility and additional features. Project requirements define only the need for a simple solution that is less flexible. Implementing these changes will result in a delay. What should the project manager do? A. Reject the proposal, and follow the project management plan. B. Escalate it to the project sponsor via a change request. C. Agree to the changes, and arrange for more resources at maintain the schedule. D. Incorporate the changes, and update the project management plan. 在項目執行階段中途一名團隊成員提出變更建議,能提供更多的靈活性和額外功能。項目需求定義僅需要具有較少靈活性的簡單解決方案,而實施這些變更將導致延期。項目經理應該怎么做? A.拒絕該建議,并遵循項目管理計劃。 B.通過變更請求將該問題上報給項目發起人。 C.同意變更,并安排更多的資源來保持進度計劃。 D.包含變更,并更新項目管理計劃。 PMP答案解析:項目范圍管理要求做且只做完成項目所需要的全部工作,要按照定義的需求來實施項目,避免渡金 PMP參考答案:A PMP考試試題二 Transferring the property of purchased software licenses to a company, s primary users is an activity of which of the following? A. Closing procurement B. Closing a project C. Validating scope D. Executing a project 將購買的軟件許可證財產轉移到一家公司的主要用戶屬于下列哪一項活動? A.采購收尾 B.項目收尾 C.核實范圍 D.執行項目 PMP答案解析:采購結束即采購收尾 PMP參考答案:A |