PMP考試每天一練-2018年PMP考試試題35
PMP考試試題一: A project manager works with the team to develop the project schedule. What information is considered a prerequisite to creating the schedule? A.Ensure the project scope is well defined B.Verify the sponsor’s approval of the business case C.Review project constraints and assumptions D.Confirm the team understands each others’ roles and responsibilities 項目經理與團隊合作,編制項目進度計劃。哪個信息被認為是創建進度計劃的前提條件? A.確保項目范圍定義充分 B.確認項目發起人批準商業論證 C.審查項目約束條件和假設 D.確認團隊了解每個其他成員的角色和職責 PMP答案解析:制定進度計劃的輸入:項目范圍說明書 PMP參考答案:A PMP考試試題二 A project with an approved charter requires resources with a specific skill set who are in high demand for similar project. Before the project management plan is finalized, the project manager recruits two skilled people for the project team.What is the project maanger performing? A. Facilitating team building B. Implementing responsibility assignment matrix (RAM) C. Planning human resource management D. Acquiring the project team 一個章程已獲批準的項目要求擁有特殊技能集的資源,但該資源在類似項目中的需求很高。最終確定項目管理計劃之前,項目經理為項目團隊招募了兩名高技能人才。項目經理執行的是下列哪一項? A.促進團隊建設 B.實施責任分配矩陣(RAM) C.制定人力資源管理計劃 D.組建項目團隊 PMP答案解析:招募,是組建項目團隊的工具 PMP參考答案:D |