PMP考試每天一練-2018年PMP考試試題49
PMP考試試題一: The project manager prepares to present the project management plan to key stakeholders for approval before moving to the execution phase. Gaining key stakeholder approval will ensure which of the following? A.The stakeholders are committed to the project B.The best resources will be assigned to the project C.The project will be completed D.The project will be on time and within budget 進入執行階段之前,項目經理準備向關鍵干系人提交項目管理計劃批準。獲得關鍵干系人批準,可確保下列哪一項? A.干系人承諾投入到該項目中 B.將最佳資源分配到項目中 C.項目將被完成 D.項目將符合時間和預算要求 PMP答案解析:獲得關鍵干系人的批準是獲得干系人的參與承諾 PMP參考答案:A PMP考試試題二 A portion of a project’s solution is estimated to cost US$75,000, and may be outsourced to a subcontractor. Before making a decision to outsource, what type of analysis should be performed? A.Earned monetary value B.Make-or-buy C.Expert judgment D.Proposal evaluation techniques 項目解決方案的其中一部分估算成本為75000美元,可以外包給一名分包商。在做出外包決定之前,應執行那種分析類型? A.掙得的貨幣價值 B.自制或外購分析 C.專家判斷 D.建議書評估技術 PMP答案解析:自行完成估算成本為75000美元,也可以進行外包,應執行自制或外購分析 PMP參考答案:B |