PMP考試每天一練-2018年P(guān)MP考試試題59
PMP考試試題一: The project manager has received several approved changes to the requirements. All changes were subject to change control. After six months, the team cannot identify the percentage of progress achieved.What should the project manager do to avoid this situation? A.Ensure that the project schedule includes all approved changes and that they are communicated to the project team. B.Schedule a weekly meeting with the team to review the project management plan and incorporate the changes accordingly C.Identify and analyze the deliverables and related work assigned to each team member D.Structure and organize the work breakdown structure 項(xiàng)目經(jīng)理已經(jīng)收到多個(gè)批準(zhǔn)的需求變更。所有變更均按照變更控制流程進(jìn)行。六個(gè)月后,團(tuán)隊(duì)無法確定已完成進(jìn)度的百分比。為避免這種情況,項(xiàng)目經(jīng)理應(yīng)該怎么做? A.確保項(xiàng)目進(jìn)度計(jì)劃包含所有批準(zhǔn)的變更,并已與項(xiàng)目團(tuán)隊(duì)溝通 B.安排與團(tuán)隊(duì)召開一次周會(huì),審查項(xiàng)目管理計(jì)劃,并包含相應(yīng)的變更 C.識(shí)別并分析可交付成果以及分配給每名團(tuán)隊(duì)成員的相關(guān)工作 D.構(gòu)造和組織工作分解結(jié)構(gòu) PMP答案解析:確保變更均按照變更控制流程進(jìn)行,并與團(tuán)隊(duì)及時(shí)溝通 PMP參考答案:A PMP考試試題二 A truck carrying critical products for a project is in a traffic accident and the products are destroyed. The project manager should refer to which of the following for a contingency plan? A. Risk reassessment B. Quantitative risk analysis C. Risk register D. Contingency reserves 一輛運(yùn)送項(xiàng)目關(guān)鍵產(chǎn)品的卡車發(fā)生交通事故,產(chǎn)品被銷毀。項(xiàng)目經(jīng)理應(yīng)參閱下列哪一份文件獲得應(yīng)急計(jì)劃? A.風(fēng)險(xiǎn)再評(píng)估 B.定量風(fēng)險(xiǎn)分析 C.風(fēng)險(xiǎn)登記冊(cè) D.應(yīng)急儲(chǔ)備 PMP答案解析:風(fēng)險(xiǎn)登記冊(cè)中包括了已識(shí)別的風(fēng)險(xiǎn)及其應(yīng)急計(jì)劃 PMP參考答案:C |