PMP考試每天一練-2018年PMP考試試題62
PMP考試試題一: A full-time project manager retains technicians from other departments for a new project, However, the technicians complain that their existing workloads are seriously affecting the new project's progress. The project manager has the right to arrange for the technicians to make completion of the new project a priority.What type of organizational structure does this describe? A. Strong matrix B. Balanced matrix C. Projectized D. Weak matrix 一位全職項目經理被授權可以調用其他業務部門的技術人員來參與新項目。當技術人員抱怨其本部門業務嚴重影響了新項目運作時,項目經理有權利協調該技術人員優先完成新項目的工作。該公司屬于以下哪個組織? A.強矩陣型組織 B.平衡矩陣型組織 C.項目型組織 D.弱矩陣型組織 PMP答案解析:典型的強矩陣組織特點,對于資源有優先支配權 PMP參考答案:A PMP考試試題二 A project manager discovers that a key team member will leave the organization in two weeks. The team member works on tasks that are on the critical path A.Evaluate the impact of losing this member B.Verify if can change the scope C.Update work breakdown structure D.Change the project team member 項目經理發現一名關鍵團隊成員將在兩周內離開組織。該名團隊成員正在為處于關鍵路徑上的任務工作。項目經理首先應該做什么 A.確定該名團隊成員的影響 B.核實是否能夠變更范圍 C.更新工作分解結構 D.更換團隊成員 PMP答案解析:首先確定失去團隊成員的影響 PMP參考答案:A |