PMP考試每天一練-2018年PMP考試試題63
PMP考試試題一: At the last minute, a project team implements a new feature that is not included in the scope statement. To obtain customer approval, what process should the project manager implement next? A.Plan Scope Management B.Validate Scope C.Perform Integrated Change Control D.Perform Qualitative Risk Analysis 在最后一刻,項目團隊實施了范圍說明書中未包含的新功能。若要獲得客戶的批準,項目經理下一步應執(zhí)行哪個過程? A. 制定范圍管理計劃 B. 核實范圍 C. 執(zhí)行整體變更控制 D. 執(zhí)行定性風險分析 PMP答案解析:得到客戶的批準,正確的做法就是通過整體變更控制,也是四個選項中最好的參考答案。 PMP參考答案:C PMP考試試題二 To officially close a project, what should the project manager do? A. Close out the risk register B. Validate scope C. Update the project management plan D. Close out procurements 正式收尾項目時,項目經理應該怎么做? A.關閉風險登記冊 B.核實范圍 C.更新項目管理計劃 D.結束采購工作 PMP答案解析:正式收尾項目時,應該先做確認范圍 PMP參考答案:B |