PMP考試每天一練-2018年P(guān)MP考試試題71
PMP考試試題一: A project manager closes out a project which includes several contractors as part of the team. The project manager also notifies the project team’s contract administrator.For proper contract closure, the project manager should ensure which of the following are updated? A.Lessons learned, deliverables acceptance, budget, and project documentation B.Lessons learned, deliverables acceptance, and procurement file C.Lessons learned, budget, and project documentation D.Lessons learned, deliverables acceptance, budget, and performance 項(xiàng)目經(jīng)理收尾一個(gè)項(xiàng)目,該項(xiàng)目包含多個(gè)承包商作為團(tuán)隊(duì)組織組成部分。項(xiàng)目經(jīng)理也通知了項(xiàng)目團(tuán)隊(duì)的合同經(jīng)理。為了進(jìn)行正確的合同收尾,項(xiàng)目經(jīng)理應(yīng)確保更新下列哪一項(xiàng)? A.經(jīng)驗(yàn)教訓(xùn)、可交付成果驗(yàn)收、預(yù)算和項(xiàng)目文檔 B.經(jīng)驗(yàn)教訓(xùn)、可交付成果驗(yàn)收和采購文件 C.經(jīng)驗(yàn)教訓(xùn)、預(yù)算和項(xiàng)目文檔 D.經(jīng)驗(yàn)教訓(xùn)、可交付成果驗(yàn)收、預(yù)算和績(jī)效 PMP答案解析:合同收尾就是結(jié)束采購,結(jié)束采購的輸出:組織過程資產(chǎn)更新(采購檔案、可交付成果驗(yàn)收、經(jīng)驗(yàn)教訓(xùn)文檔) PMP參考答案:B PMP考試試題二 In a functional organization structure, a project with a critical completion date fails behind schedule, but according to the earned value analysis, it is still under budget. To deliver the project on time, the project manager suggests adding five skilled resources What should the project manager do next? A.Update the human resource management plan and the schedule baseline B.Present the change request to the change control board for approval C.Present the change request to the project sponsor for approval D.Add additional resources as there are sufficient funds available 在一個(gè)職能型組織結(jié)構(gòu)中,擁有關(guān)鍵完工日期的項(xiàng)目落后于進(jìn)度,但是按照掙值分析,目前仍低于預(yù)算。為了按時(shí)交付項(xiàng)目,項(xiàng)目經(jīng)理建議增加五個(gè)技能嫻熟的資源。項(xiàng)目經(jīng)理接下來應(yīng)該怎么做? A.更新人力資源管理計(jì)劃和進(jìn)度基準(zhǔn) B.將變更單提交給變更控制委員會(huì)批準(zhǔn) C.向項(xiàng)目發(fā)起人提交變更請(qǐng)求,用于批準(zhǔn) D.增加額外的資源,因?yàn)橛谐渥愕目捎觅Y金 PMP答案解析:進(jìn)度落后,低于預(yù)算,PM建議增加額外資源來進(jìn)行進(jìn)度壓縮。增加額外資源可能會(huì)花額外的錢,也需要?jiǎng)佑霉芾韮?chǔ)備,會(huì)影響成本基準(zhǔn),需要CCB來批準(zhǔn) PMP參考答案:B |