PMP考試每天一練-2018年P(guān)MP考試試題75
PMP考試試題一: A new project manager works on a project that involves the purchasing of machinery. A colleague worked with the same supplier on a similar project that had a major issue that delayed the machinery delivery. The project manager meets with the colleague to ask about related issue with the supplier.What activity is the project manager performing? A.Plan Procurements B.Plan Risk Management C.Shortlist Supplier D.Plan Schedule 新項目經(jīng)理管理一個涉及機械采購的項目。一名同事曾經(jīng)在類似項目上同一個供應(yīng)商合作過,而該類似項目發(fā)生了一個重大問題,延遲了機械交付。項目經(jīng)理與該同事會面詢問該供應(yīng)商有關(guān)問題。項目經(jīng)理執(zhí)行的是哪項活動? A.規(guī)劃采購 B.規(guī)劃風(fēng)險管理 C.列出供應(yīng)商清單 D.規(guī)劃進度 PMP答案解析:規(guī)劃采購管理包括如何識別預(yù)審合格的賣方 PMP參考答案:A PMP考試試題二 A developer assigned to a task with a 10-day duration completes 50% of the task. During a weekly status review session, the project manager discovers a team member wants to work overtime for three day to complete the task.What is the task’s earned value? A.7 days B.6.25 days C.5 days D.4 days 分配到一個為期10天任務(wù)的開發(fā)人員完成了50%的任務(wù)。在每周狀態(tài)評審會上,項目經(jīng)理發(fā)現(xiàn)團隊成員希望加班工作三天來完成。該任務(wù)該任務(wù)的掙值是多少? A.7天 B.6.25天 C.5天 D.4天 PMP答案解析:50%*10=5天 PMP參考答案:C |