PMP考試每天一練-2018年PMP考試試題77
PMP考試試題一: A customer learns that a requirement will not be met unless a task that was not identified during planning is added to the project. A team fielder successfully executes the task and later inform the project manager during a weekly meeting. Despite the favorable outcome, the project manager is unhappy with this information, since the task did not have the necessary approval. What plan outlines the requirement for approval? A.Risk management B.Change management C.Scope management D.Cost management 客戶意識到除非在項目中添加一項在規劃期間未識別到的任務,否則將不滿足要求。團隊成員成功執行了這項任務,并在之后的一次周會上通知項目經理。即使是有利的結果,但項目經理對這個信息感到不滿,因為任務沒有得到必要的批準。哪一份計劃概述了批準要求? A.風險管理 B.變更管理 C.范圍管理 D.成本管理 PMP答案解析:變更管理計劃將對如何變更做出詳細規定 PMP參考答案:B PMP考試試題二 While acquiring resources for a strategic project, the project manager discovers that a key resource will not be available to perform a project task. Assuming the task on the critical path, what strategy should be used to mitigate this issue. A.Attempt to reduce the project scope B.Obtain permission to work on the weekends C.Extend the project’s end-date and resolve the issue at a later project stage D.Assign a less-skilled resource on the project and increase the task duration 在為一個戰略項目招募資源時,項目經理發現一名關鍵資源將不能執行項目任務。假設該任務的計劃不處于關鍵路徑上,應使用什么戰略來減輕這個問題? A. 嘗試減少項目范圍 B. 獲得在周末工作的許可 C. 延長項目結束日期并在項目后期解決該問題 D. 為項目分配一個技能略差的資源,并增加任務持續時間 PMP答案解析:如因制約因素(如經濟因素或其他項目對資源的占用)而無法獲得所需人力資源,在不違反法律、規章、強制性規定或其他具體標準的前提下,項目經理或項目團隊可能不得不使用替代資源(也許能力較低) PMP參考答案:D |