PMP考試每天一練-2018年PMP考試試題102
PMP考試試題一: A company is awarded a contract to develop a product's manufacturing assembly line. The customer has concerns regarding a potential risk to a critical component. Which of the following will help the team move to the project's design phase? A.Develop a prototype. B.Perform benchmarking C.Conduct a customer workshop. D.Conduct Six Sigma analysis. 公司獲得一項合同,開發一種產品的生產組裝線?蛻魧σ粋關鍵組件的潛在風險十分擔心。下列哪一項將幫助團隊進入項目的設計階段? A.開發原型。 B.執行標桿對照。 C.召開客戶研討會。 D.開展六西格瑪分析。 PMP答案解析:題干說客戶對一個潛在風險十分擔心,而“原型法”可以幫助減輕風險,并且也是收集需求的一種方法 PMP參考答案:A PMP考試試題二 A project manager works on a US$3 million project which involves two suppliers. The project manager creates a statement of work(SOW) for each supplier A.Risk management plan B.Project charter C.Procurement management plan D.Supplier scope statement 項目經理正在管理價值300萬美元,涉及兩個供應商的項目。項目經理為每名供應商創建了一份工作說明書(SOW).下列哪一項需要SOW的信息 A.風險管理計劃 B.項目章程 C.采購管理計劃 D.供應商范圍說明書 PMP答案解析:SOW是制定項目章程的輸入 PMP參考答案:B |