PMP考試每天一練-2018年PMP考試試題108
PMP考試試題一: A change request for additional features was approved at the last project steering committee meeting. What should the project manager do next? A.Direct the development team to continue with the current project management plan B.Update the project management plan and other necessary project documentation C.Meet with the development team to discuss the change request D.Direct the development team to complete the additional features 在最近一次項目指導委員會會議上,額外功能的變更請求獲得批準。項目經(jīng)理接下來應該怎么做? A.指示開發(fā)團隊繼續(xù)當前的項目管理計劃 B.更新項目管理計劃和其他必要的項目文檔 C.與開發(fā)團隊開會,討論變更請求 D.指示開發(fā)團隊完成額外功能 PMP答案解析:變更請求獲得批準后,下一步是更新項目管理計劃/項目文件 PMP參考答案:B PMP考試試題二 During project implementation, a stakeholder indicates that some deliverables do not comply with specifications. The project manager states these specifications were discussed in project meetings, and the agreed outcomes were communicated and documented in published reports.To avoid this outcome, what should have been done in the planning phase? A.Analyzed communication requirements in the stakeholder management plan B.Included the stakeholders in the quality management plan preparation C.No action is necessary, the stakeholder should have reviewed the distributed information D.Addressed deliverables and expectations at the kick-off meeting 在項目實施期間,一名干系人指出某些可交付成果不符合規(guī)范要求。項目經(jīng)理表示規(guī)范要求已在項目會議上討論過,并已溝通了約定成果,記錄在發(fā)布的報告中。為避免這種情況,在規(guī)劃階段應完成那一項工作? A.在干系人管理計劃中分析溝通需求 B.將干系人包含在質量管理計劃準備過程中 C.沒有必要采取任何行動, 干系人應以查看分發(fā)的所有信息 D.在項目啟動大會上公布可交付成果和期望 PMP答案解析:干系人指出可交付成果不符合規(guī)范要求,說明是質量不達標。那么應該做好質量管理,盡早讓干系人參與到質量管理計劃中 PMP參考答案:B |