PMP考試每天一練-2018年PMP考試試題112
PMP考試試題一: During a project’s execution in a weak matrix organization, the functional manager, project sponsor, and project manager discuss how to improve a team member’s knowledge and skills. Who is responsible to address these needs? A.Functional manager B.Human resource department C.Project manager D.Project sponsor 在一個弱矩陣式組織中的項目執行期間,職能經理、項目發起人和項目經理討論如何提高團隊成員的知識和技能。誰應該負責解決這些需求? A.職能經理 B.人力資源部門 C.項目經理 D.項目發起人 PMP答案解析:弱矩陣環境中,職能經理的權力大于項目經理 PMP參考答案:A PMP考試試題二 Which of the following is the final task in a project? A. Completing a lessons learned review and update B. Transporting the accepted deliverables to the client C. Archiving the project records D. Disbanding the project team 下列哪一項屬于一個項目的最終任務? A. 完成經驗教訓審查和更新 B. 將已驗收的可交付成果運送給客戶 C. 項目記錄存檔 D. 解散項目團隊 PMP答案解析:收尾的最后一步,資源解散 PMP參考答案:D |