PMP考試每天一練-2018年PMP考試試題115
PMP考試試題一: During a project, the project manager is informed of new requirements that need to be delivered. The project manager also learns that two resources will be removed from the project, which will impact the schedule.To evaluate the impact of these changes and risks to the project’s execution, what should the project manager reference? A.Project management plan B.Work breakdown structure C.Resource schedule D.Change management plan 在項目期間,項目經理收到交付新需求的通知。項目經理還了解到兩名資源將從項目離開,從而影響了進度。為了評價這些變更和風險對項目執行的影響,項目經理應查閱那一份文件? A.項目管理計劃 B.工作分解結構 C.資源進度計劃 D.變更管理計劃 PMP答案解析:變更和風險,綜合來看需要查閱項目管理計劃 PMP參考答案:A PMP考試試題二 A project with an estimated cost of US$5 million is approved and funded. The project manager is entitled to a 1% bonus on any cost savings if the project finishes under US$5 million. At the completion of the project, the actual cost savings and the bonus amount paid should be documented and archived.This information could be used in future projects for which of the following purposes? A.Estimating the budget B.Determining the project manager’s future compensation C.Assisting in future vendor selections D.Adding to the lessons learned document repository 估算成本為500萬美元的項目已獲批準且資金到位。如果項目在500萬美元以內完成,項目經理將根據節省的任何成本,有權獲得1%的獎金。在項目完成時,應記錄并存檔節省的實際成本和支持的資金金額、該信息可以出于下列哪一種目的在未來項目中使用? A.估算預算 B.確定項目經理的未來補償 C.幫助未來的供應商選擇 D.添加到經驗教訓文檔庫中 PMP答案解析:將這些信息添加到經驗教訓文檔中,供未來項目參考 PMP參考答案:D |