PMP考試每天一練-2018年P(guān)MP考試試題126
PMP考試試題一: A contract for a company’s software solution is awarded to a vendor. After implementation the company’s users find issues that the company’s support team must address. Key clauses in the support agreement, which were included in the procurement contract, are unclear and biased towards the vendor.On which of the following processes should the project manager have focused to avoid the conflict? A.Plan procurement management B.Conduct procurements C.Manage procurements D.Contract procurements 一家公司的軟件解決方案合同授于賣方。實施之后,該公司的用戶發(fā)現(xiàn)了一些該公司支持團隊必須 解決的問題。包含在采購合同中的支持協(xié)議關(guān)鍵條款不明確,全偏向于賣方。 A. 制定采購管理計劃 B. 實施采購 C. 管理采購 D. 控制采購 PMP答案解析:On which of the following processes should the project manager have focused to avoid the conflict?題目問的是本應(yīng)該關(guān)注哪個過程組。 PM本應(yīng)該關(guān)注實施采購過程,合同的正式授予。 PMP參考答案:B PMP考試試題二 A team is not able to follow the project specifications. However, there is no formal report of this issue. As a result, the project manager cannot confirm that the team is technical competence to perform the work.What should the project manager do next? A.Request a quality audit review by the quality assurance team B.Perform the control quality process C.Review the situation with the project’s sponsor D.Ask the team members about their technical issues in meeting the project requirements 團隊不能遵循項目技術(shù)規(guī)范。但是,沒有這個問題的正式報告。結(jié)果,項目經(jīng)理無法確認團隊是否有執(zhí)行工作的技術(shù)能力項目經(jīng)理接下來應(yīng)該怎么做? A.申請由質(zhì)量保證團隊進行質(zhì)量審計審查 B.執(zhí)行質(zhì)量控制流程 C.與項目發(fā)起人審查這種情況 D.詢問團隊成員有關(guān)他們滿足項目要求的技術(shù)問題 PMP答案解析:題干說團隊不能遵循項目技術(shù)規(guī)范, PM接下來應(yīng)該執(zhí)行質(zhì)量審計。質(zhì)量審計是用來確定項目活動是否遵循了組織和項目的政策、過程與程序 PMP參考答案:A |