PMP考試每天一練-2018年PMP考試試題137
PMP考試試題一: A project manager identifies a risk on a project which causes work to stop. The project team was forced to use a contingency plan In what project management process group is the project manager currently in? A.Control risk B.Plan risk responses C.Identify risks D.Mitigate risks 項目經理識別到項目上的一個風險可能導致停工。項目團隊被迫使用應急計劃項目經理目前處于那一個項目管理過程組? A.控制風險 B.規劃風險應對 C.識別風險 D.減輕風險 PMP答案解析:實施應對計劃是控制風險過程 PMP參考答案:A PMP考試試題二 During the planning phase, the project team gathers requirements from the client on multiple occasions with multiple team members. Which of the following group creativity techniques would assist the project team and the client to generate and collect multiple ideas related to the requirements? A.Observations B.Questionnaires and surveys C.Prototypes D.brainstorming 在項目規劃階段,項目團隊采用多名團隊成員在多種場合收集客戶的需求。下列哪一項群體創新技術將幫助項目團隊和客戶產生的收集與需求有關的多種創意? A.觀察 B.問卷調查 C.原型法 D.頭腦風暴法 PMP答案解析:四個選項都是收集需求的工具,題目問的是收集需求的群體創新技術,頭腦風暴 PMP參考答案:D |