PMP考試每天一練-2018年PMP考試試題142
PMP考試試題一: Early in a project's life cycle, a project manager plans to enhance the project's chance of success by building partnerships and coalitions with project stakeholders. What should the project ragger do to achieve this? A.Create a stakeholders engagement assessments matrix to identify gaps between current and desired engagement levels. B.Map the interest levels of each stakeholder to the project's objectives. C.Document and clarify stakeholder roles by developing a responsible, accountable, consult, and inform (RACI) matrix D.Gather and analyze information on potential stakeholders to determine whose interests should be considered. 在項目生命周期早期,項目經理打算通過與項目干系人建立合作伙伴關系和聯合體,提高項目的成功概率。若要實現這一點,項目經理應該怎么做? A.創建項目干系人參與評估矩陣,識別當前參與程度與所需參與程度之間的差距。 B.將每位項目干系人的利益層級與項目目標映射。 C.通過制定一份執行、負責、咨詢和知情(RACI)矩陣記錄并澄清干系人的角色。 D.收集并分析潛在干系人的相關信息,確定應考慮誰的利益。 PMP答案解析:A參考答案為制定干系人管理計劃,B為干系人分析,C為RACI,D參考答案為識別干系人。題干提示為項目生命周期早期,首先做識別干系人 PMP參考答案:D PMP考試試題二 During the customer’s final acceptance of deliverables, the project manager encounters opposition from a local group. The project manager’s company conducts a root cause analysis and discovers that the project did not adequately consider environmental factors for the project.During which process should this have been completed? A.Initiating B.Monitoring and controlling C.Planning D.Executing 在客戶最終驗收可交付成果期間,項目經理遭遇到其他地方團隊的反對意見。項目經理所在公司開展了一次根本原因分析,發現項目并未充分考慮項目的環境因素。這本應該在下列那一個過程中完成? A.啟動 B.監控 C.規劃 D.執行 PMP答案解析:項目經理必須在每個過程中考慮組織過程資產和事業環境因素,即使它們沒有被明確地列為輸入,盡早考慮組織過程資產和事業環境因素 PMP參考答案:A |