PMP考試試題一: During final product testing of a two-year project, an application is scheduled to be implemented within the next month. The project manager discovers that a mandatory deliverable was overlooked in the project management plan; however, the development team states that it will only take 15 days to complete.What should the project manager do? A.Re-validate the scope B.Perform integrated change control C.Adjust the schedule to cover the change D.Perform crashing to meet the deadline 在一個(gè)為期兩年項(xiàng)目的最終產(chǎn)品測(cè)試期間,一項(xiàng)應(yīng)用程序安排在下個(gè)月實(shí)施。項(xiàng)目經(jīng)理發(fā)現(xiàn)項(xiàng)目管理計(jì)劃中忽略了一個(gè)強(qiáng)制性可交付成果。然而,開發(fā)團(tuán)隊(duì)說(shuō)只需花15天能夠完成。項(xiàng)目經(jīng)理應(yīng)該怎么做? A. 重新核實(shí)范圍 B. 實(shí)施整體變更控制 C. 調(diào)整進(jìn)度計(jì)劃包含變更 D. 執(zhí)行趕工,滿足期限要求 PMP答案解析:“忽略了一個(gè)強(qiáng)制性可交付成果”,說(shuō)明與原計(jì)劃有偏差,需要變更 PMP參考答案:B PMP考試試題二 The most likely cost for an activity is US$2,000. The optimistic cost is US$1,500. The pessimistic cost is US$3,100.What would be the expected activity cost? A.US$2,000 B.US$2,100 C.US$2,300 D.US$3,100 某項(xiàng)活動(dòng)的最可能成本是2000美元。樂觀成本是1500美元。悲觀成本是3100美元。那么預(yù)期活動(dòng)成本是多少? A.2000美元 B.2100美元 C.2300美元 D.3100美元 PMP答案解析:三點(diǎn)估算公式:(1500+4*2000+3100)/6=2100 PMP參考答案:B |