PMP考試每天一練-2018年PMP考試試題160
PMP考試試題一: A project is 40% complete. To increase team productivity and improve the implementation of processes. Which of the following should the project manager conduct? A.Brainstorming session B.Risk audit C.Process optimization audit D.Quality audit 項目已完成40%。若要提高團隊生產力,改善流程的執行。項目經理應該開展下列哪一項? A.頭腦風暴法 B.風險審計 C.過程優化審計 D.質量審計 PMP答案解析:質量審計的目標:積極、主動地提供協助,以改進過程的執行,從而幫助團隊提高生產力。 PMP參考答案:D PMP考試試題二 Two co-workers disagree on the products and services that will be delivered by a project.To address the disagreement, the project manager should refer to which of the following? A. Project statement of work (SOW) B. Human resource management plan C. Quality management plan D. Project management plan 兩名同事對一個項目交付的產品和服務意見不一致。若要解決這個分歧,項目經理應該查閱下列哪一份文件? A.工作說明書(SOW) B.人力資源管理計劃 C.質量管理計劃 D.項目管理計劃 PMP答案解析:查詢之前的經驗教訓提高個人交付項目的成功率 PMP參考答案:A |