PMP考試每天一練-2018年PMP考試試題162
PMP考試試題一: A project requires internal resources and external resources. External resources are acquired through a standard procurement plan. After a hurricane strikes the contracted supplier’s location, they can no longer meet the required timeline for the deliverables Which contractual component will clarify the financial resolution of the supplier’s failure to meet contracted terms? A.Force majeure clause B.Incentive clause C.Reimbursement clause D.Arbitration clause 一個項目需要內部資源和外部資源。外部資源通過一份標準采購計劃獲得。在一場颶風襲擊分包供應商所在地后,他們無法滿足可交付成功要求的時間限制。哪一個合同部分將澄清供應商未能滿足該合同條款的財務解決方式? A.不可抗力條款 B.激勵條款 C.補償條款 D.仲裁條款 PMP答案解析:颶風是不可抗力因素 PMP參考答案:A PMP考試試題二 Project team members feel empowered to work independently and believe that the project manager trusts them to deliver their tasks without managing the team too closely.Which management style does the project manager demonstrate? A.Need for affiliation B.Theory x C.Theory y D.Need for power 項目團隊成員認為能夠獨立工作,并認為項目經理信任他們能在不嚴密管理團隊的情況下交付任務。項目經理證明的是哪一種管理方式? A歸屬需求 B.X理論 C.Y理論 D.權力需求 PMP答案解析:人之初,性本勤 PMP參考答案:C |