PMP考試每天一練-2018年PMP考試試題165
PMP考試試題一: A project that is 25% complete has a budget at completion of US$100,000, and an actual cost of US$50,000. Assuming that the remaining work will be performed at the same cost performance index incurred, what is the project’s estimate at completion? A.US$200,000 B.US$150,000 C.US$125,000 D.US$75,000 一個已經完成25%的項目完工預算為100000美元,而實際成本為50000美元。假設剩余工作將按已發生的相同成本績效指數執行,則項目的完工估算是多少? A.200000美元 B.150000美元 C.125000美元 D.75000美元 PMP答案解析:典型偏差,CPI=EV/AC=(25%*10W)/5W=0.5,EAC=BAC/CPI=10W/0.5=20W PMP參考答案:A PMP考試試題二 A project team identifies the risks within the project. Which of the following techniques should the project team use? A.Assess risk priorities B.Review lessons learned C.Perform a sensitivity analysis D.Gather data and representations 項目團隊識別了項目當中的風險。項目團隊應使用下列哪一項技術? A.評估風險優先級 B.審查經驗教訓 C.執行敏感性分析 D.收集數據和展示 PMP答案解析:識別風險后,需要進行風險定性分析。C和D是風險定量分析的技術 PMP參考答案:A |