PMP考試每天一練-2019年PMP考試試題1
PMP考試試題一: A new warehouse is ready for operations. Before operations begin, the project manager must prepare the final project report. To what should the project manager refer? A. Lessons learned, project charter, and work breakdown structure (WBS) B. Project baselines, accepted deliverables, and earned value (EV) C. Checklists, responsibility assignment matrix(RAM), and risk management plan D. Accepted deliverables, lessons learned, and transition criteria 一個新的倉庫準備好運營。運營開始之前,項目經理必須準備最終項目報告。項目經理應該查閱哪些文件? A.經驗教訓、項目章程和工作分解結構(WBS) B.項目基準、已驗收的可交付成果和掙值(EV) C.核對表、責任分配矩陣(RAM)和風險管理計劃 D.已驗收的可交付成果、經驗教訓和移交標準 PMP答案解析:四個答案中,做為項目轉入運營之前的最終報告,最好的內容是答案D PMP參考答案:D PMP考試試題二 Before the stakeholder meeting. What communication method should the project manager use to obtain key stakeholder approval of the project management plan? A.Email B.Interactive C.Pull D.push 在干系人會議之前,項目經理應使用什么溝通方式獲得干系人對項目管理計劃的認可? A.電子郵件 B.交互式溝通 C.拉式溝通 D.推式溝通 PMP答案解析:交互式溝通 PMP參考答案:B |