PMP考試每天一練-2019年P(guān)MP考試試題23
PMP考試試題一: During a project’s testing phase, the project team learns of a software tool that could have reduced the project’s development effort by40 days. Where should this be recorded A. Procurement documents B. Project or phase closure documents C. Lessons learned knowledge base D. Change log 在項目的測試階段,項目團隊得知一款軟件工具能夠減少項目的開發(fā)工作40天時間。這些應(yīng)記錄在哪里? A.采購文件 B.項目或階段收尾文件 C.經(jīng)驗教訓(xùn)知識庫 D.變更日志 PMP答案解析:無論是團隊生成的經(jīng)驗教訓(xùn)還是團隊獲取的經(jīng)驗教訓(xùn),都屬于經(jīng)驗教訓(xùn)知識庫 PMP參考答案:C PMP考試試題二 During a team meeting, the project manager collects information for the project charter. Which of the following will be included in the project charter? A.Assumptions and constraints, high-level risks, and stakeholder list B.Project purpose, summary budget, and project management plan C.Scope baseline, team composition, and project management plan D.Assumptions and constraints, work breakdown structure, and summary budget 項目經(jīng)理在團隊會議上收集項目章程信息。下列哪一項應(yīng)包含進項目章程 A.假設(shè)和制約因素、高層次風(fēng)險以及干系人名單 B.項目目的、預(yù)算匯總和項目管理計劃 C.范圍基準(zhǔn)、團隊構(gòu)成和開支限制 D.假設(shè)和制約因素、工作分解結(jié)構(gòu)和預(yù)算匯總 PMP答案解析:項目章程中沒有項目管理計劃,排除B。章程中也沒有 C,排除 C。章程中沒有工作分解結(jié)構(gòu),排除D PMP參考答案:A |