PMP考試每天一練-2019年PMP考試試題26
PMP考試試題一: During project execution, the customer directly contacts the project manager to request the addition of a testing task and is willing to pay the corresponding fees. However, the customer requests that the project be completed no later than the current completion time. Since it is possible to complete the task with the staff and facilities available, the company asks the project team to take on the new testing task. However, the company does not charge for the extra cost, which includes personnel and testing facilities. Furthermore, the execution of the new task will impact the schedule or quality of the existing project. How should the project manager handle the customer's request? A.Communicate with the company about setting up another project team to accept the new task. B.Alert the client that it is not possible to complete the new task with the resources available for the project. C.Accept the new task and request that the project members work overtime to ensure its completion, as it will bring in" extra revenue for the company. D.Lower the standards for. completing the current task as appropriate, and complete the current project ahead of schedule to ‘make time for completing the new task. 在某項目實施過程中,客戶直接聯系項目經理要求新增一項測試任務,并且愿意支付相應的費用,但要求完成的時間不遲于現有項目要求執行完成的時間。由于該任務利用現有項目人員和設備就能夠完成,公司要求項目組承擔這個新增測試任務,但并沒有提供額外的成本,包括人員和測試設備。而該新增任務的執行會影響到現有項目的進度或質量,項目經理應該如何處理這個客戶需求? A.和公司溝通另外成立一個項目組接受新增任務。 B.通知客戶項目現有資源無法完成這個新增任務。 C.接受該新增任務,要求項目成員加班完成,因為會為公司帶來額外收益。 D.適當降低現有任務完成的標準,提早完成現有項目,擠出時間完成新增任務 PMP答案解析:根據題干描述,四個選項中,A答案是最優選項 PMP參考答案:A PMP考試試題二 Accompany provides the following annual data for the cost of quality (COQ): To reduce overall appraisal costs, on what should the company focus? A.Rework B.Documentation of processes C.Testing D.Training 公司提供了以下質量成本(COQ)的年度數據:為了降低總體評價成本,公司應該重點關注哪一點? A.返工 B.過程文檔 C.測試 D.培訓 PMP答案解析:B、C、D都屬于一致性成本,其中過程文檔和培訓屬于預防成本,測試屬于評價成本 PMP參考答案:C |