PMP考試每天一練-2019年PMP考試試題28
PMP考試試題一: A manufacturing team completes installation of a panel for a client's access control system. After a quality check, the project manager discovers multiple issues and submits a. change request. What type of change request is this? A.Preventive action B.Defect repair C.Corrective action D.Product update 制造團隊完成客戶訪問控制系統的面板安裝。經過質量檢查,項目經理發現多個問題,并提交變更請求。這屬于哪一類型的變更請求? A.預防措施 B.缺陷補救 C.糾正措施 D.產品更新 PMP答案解析:修正不一致產品或組件的有目的活動,即為缺陷補救 PMP參考答案:B PMP考試試題二 There is a potential delay in the internal manufacturing of materials. It is decided that part of the materials will be bought from a third-party manufacturer A.select sellers B.procurement statement of work C.requirements documentation D.independent estimates 內部材料制造存在發生延期的可能性。決定部分材料從某一第三方制造商采購。項目經理接下來該做什么? A.選擇賣方 B.采購工作說明書 C.需求文檔 D.獨立估算 PMP答案解析:決定將工作外包,接下來就要編制采購工作說明書 PMP參考答案:B |