PMP考試每天一練-2019年PMP考試試題30
PMP考試試題一: A project manager must carry out the design and implementation of a quality management system under ISO 9001 standards. What should the project manager do? A.Conduct a project kick-off meeting. B.Develop a detailed project schedule. C.Request project funding. D.Prepare a project management plan. 項目經理必須根據IS0 9001標準進行一個質量管理系統的設計和實施。項目經理應該怎么做? A.召開項目啟動大會。 B.制定詳細的項目進度計劃。 C.請求項目資金。 D.準備項目管理計劃。 PMP答案解析:推薦C答案,項目啟動需要有發起人提供資金和資源支持 PMP參考答案:C PMP考試試題二 A company hires a consultant to implement third-party software. The project has multiple phases and must implement phase one within 18 months.Which of the following risks must be captured in the project charter? A. Vendor resources may be unavailable on the project’s start date B. Project resources are not properly trained on the new software C. Detailed project scope is incomplete D. Feasibility studies determined that in-house implementation is the best solution 公司雇傭了一家顧問公司來實施第三方軟件。項目分多個階段,且必須在18個月內實施第一階段。下列哪一項風險應包含進項目章程中? A.在項目開始日期供應商資源可能不可用 B.項目資源未接受有關新軟件的正式培訓 C.詳細項目范圍不完整 D.可行性研究確定內部實施是最佳解決方案 PMP答案解析:ABD是比較具體的風險,C是模糊高層級風險,應包含在章程中 PMP參考答案:C |