PMP考試每天一練-2019年PMP考試試題36
PMP考試試題一: A project manager discovers that the critical ratio is 0.7. What does this indicate? A. The cost performance Index (CPI) is better than planned. B. The CPl is worse than planned C. The project's progress is worse than planned. D. The project's progress is better than planned.. 項目經理發現臨界比是0.7。這說明什么? A成本績效指數(CPI)比計劃好 B.CPI比計劃差 C.項目進展比計劃差 D.項目進展比計劃好 PMP答案解析:臨界比的計算方法是CPI*SPI,臨界比等于0.7,說明項目進展不好 PMP參考答案: PMP考試試題二 After confirming the availability of human resource and obtaining teams for project assignments, the project manager discovers that the resources will not sufficiently meet the project schedule. The project manager meets with a functional manager who agrees to make additional resources available for the duration of the project.What tool or technique does the project manager use? A.Negotiation B.Acquisition C.Pre-assignment D.Co-location 確認人力資源可用性并獲得執行項目任務的團隊后,項目經理發現資源不足以滿足項目進度計劃,項目經理與職能經理開會,職能經理同意為項目工期增加可用資源。項目經理是用的是什么工具或技術 A.談判 B.招募 C.預分派 D.集中辦公 PMP答案解析:“項目經理與職能經理開會”來獲得資源,這是談判 PMP參考答案:A |