PMP考試每天一練-2019年PMP考試試題41
PMP考試試題一: A company must deliver a project on a specific date without delays. However, the project has limited resources and a degree of uncertainty.When developing the project schedule, what should the project manager do to minimize the risk of delays? A.perform a schedule compression B.establish buffers for paths joining the critical chain C.communicate delays to the sponsors D.assign additional resources to critical path activities 公司必須在沒有延期的情況下按規定日期交付項目,然而,項目的資源有限,并有一定程度的不確定性。當制定項目進度計劃時,項目經理應該怎么做來盡可能減少延期風險? A.執行進度壓縮。 B.確定加入關鍵鏈路徑的緩沖時間。 C.向項目發起人溝通延遲問題。 D.向關鍵路徑活動分配額外資源。 PMP答案解析:資源有限,在關鍵鏈末端放項目反沖緩沖以應對項目延期的風險 PMP參考答案:B PMP考試試題二 Pursuant to an agreement entered into with the customer, a company selects a foreign country in which to carry out a project. Completing the project on time will require hiring 30 resources and incur overtime costs. What should the project manager consider a priority when selecting the project location? A. Internal company policies B. Overall project budget C. Customer agreement D. Project business environment 根據與客戶已簽訂的協議,公司在海外選定一個國家進行一個項目。項目需要雇傭30個人工作并需要加班以按時完成項目。在選擇項目地點時,項目經理應優先考慮以下哪項? A.公司內部政策 B.整體項目預算 C.與客戶簽訂的協議 D.項目的事業環境因素 PMP答案解析:推薦D答案,海外項目需要考慮國際政治文化,用工合規性等等方面的事業環境因素,客戶協議也屬于事業環境因素的一項 PMP參考答案:D |