PMP考試每天一練-2019年PMP考試試題47
PMP考試試題一: After a product defect is identified, a new software feature is added to improve performance. What tool or technique should confirm the feature's effectiveness? A. Ishikawa diagram B. Cost-benefit analysis C. Quality audit D. Affinity diagram 識別到產品缺陷后,增加新的軟件功能來提高性能。哪些工具或技術應該確認該功能的有效性? A.石川圖 B.成本效益分析 C.質量審計 D.親和圖 PMP答案解析:增加了新功能來提高性能,通過進行質量審計,添加該功能的有效性 PMP參考答案:C PMP考試試題二 A project manager prepares to implement a new project in which several cross-organizational business owners are involved in the planning and design. The product, s sale price is not yet approved as the project’s scope has still not been agreed upon. Further delays will impact the design and production, and slippage may occur during implementation. Since a yearly bonus may be lower as a result, one manager is pushing to start product development.What should the project manager do to address this situation? A. Obtain high-level permission to start development of the product “as is” B. Start the development of the product C. Validate the scope before starting product development D. Allow the business owners to make the decision 項目經理準備實施一個新項目,在這個項目的規劃和設計階段,涉及跨組織業務所有者。因為項目未達成一致意見,產品的銷售價格還未獲得批準。進一步延期將影響設計和生產,且在實施過程中可發生偏移。由于年終獎金可能較低,結果—名經理催促開始產品開發。為了解決這種情況,項目經理應該怎么做? A.獲得高層次許可,“按現狀”開始產品開發 B.開始產品開發 C.開始產品開發之前核實范圍 D.允許業務所有者做出決定 PMP答案解析:首先獲得高層次許可,這是制訂項目章程需要做的事。按“現狀”開始產品開發,因為項目的漸進明細 PMP參考答案:A |