PMP考試每天一練-2019年PMP考試試題55
PMP考試試題一: A project manager is responsible for the development of a unique product that will soon be released to the market. Many of the key components are complex, and the product is being developed in a fast and changing environment. How should the project manager approach quality management? A. Update the project scope as information becomes available B. Use the plan-do-check-act (PDCA) cycle as the basis for continuous Qualityimprovement C. Implement a change control system to avoid scope creep. D. Develop interrelationship diagraphs. 項目經理負責一個獨特產品的開發,該產品將很快在市場上發布。許多關鍵部件很復雜,并且產品是在一個快速和變化的環境中開發。項目經理應該如何處理質量管理? A.在信息可用時更新項目范圍。 B.用計劃—實施—檢查—行動(PDCA)循環作為持續質量改進的基礎。 C.實施變更控制系統避免范圍蔓延。 D.關聯圖。 PMP答案解析:B、D答案與質量管理有直接關系,本題目描述有敏捷和迭代項目的特點,PDCA可以理解迭代管理的一種方式 PMP參考答案:B PMP考試試題二 Two experts provide contradicting input on a technical issue. To resolve this, the project manager facilitates a meeting. The issue could not be settled during the meeting and was postponed for future resolution by others.The project manager used which of the following conflict resolution techniques? A. Withdraw/Avoid B. Compromise/Reconcile C. Smooth/Accommodate D. Collaborate/Problem Solve 兩名專家對某個技術問題提供了互相沖突的意見。為解決這個問題,項目經理召開了一次會議。但 這個問題沒有在會議上得以解決,被推遲到未來由其他人解決。項目經理使用的是下列哪一項沖突解決技術? A.撤退/回避 B.妥協/調和 C.緩解/包容 D.合作/解決問題 PMP答案解析:問題沒有解決,只是被推遲 PMP參考答案:A |