PMP考試試題一: A project manager is required to complete a project in three months, which allows insufficient time for selecting the optimum supplier. The project manager selects a supplier with whom they have worked before and signs a contract. What is the risk in this situation? A. Lack of a legally binding agreement B. Lack of proper scope definition C. Ability of the supplier to deliver the goods D. Collusion between the supplier and the project manager 項(xiàng)目經(jīng)理需要在三個(gè)月內(nèi)完成一個(gè)項(xiàng)目,這使得沒有足夠的時(shí)間選擇最佳的供應(yīng)商。項(xiàng)目經(jīng)理選擇了與他們以前合作過的供應(yīng)商并簽訂合同。這種情況的風(fēng)險(xiǎn)是什么? A.缺乏具有法律約束力的協(xié)議 B.缺乏適當(dāng)?shù)姆秶x C.供應(yīng)商交付貨物的能力 D.供應(yīng)商和項(xiàng)目經(jīng)理之間相互勾結(jié) PMP答案解析:本題意表明采用了單一來(lái)源供應(yīng)商,會(huì)有交付風(fēng)險(xiǎn) 解析:C PMP參考答案: PMP考試試題二 A new team member with no practical project experience is assigned to an ongoing project. The project manager assigns a difficult task to the new team member.What action should the project manager now take? A. Assign a mentor for the new team member and closely monitor their progress B. Recommend that the new member undertake a self-study training program C. Allow the new team member to work alone, but report daily to the project manager. D. Provide the new team member with the project management plan and assign a contact person. 一名沒有實(shí)際項(xiàng)目經(jīng)驗(yàn)的新團(tuán)隊(duì)成員被分配到一個(gè)正在進(jìn)行當(dāng)中的項(xiàng)目。項(xiàng)目經(jīng)理向該團(tuán)隊(duì)成員分配了一項(xiàng)困難任務(wù)。項(xiàng)目經(jīng)理現(xiàn)在應(yīng)該采取什么措施? A.為該新團(tuán)隊(duì)成員分配一位指導(dǎo)者,并密切監(jiān)測(cè)他們的進(jìn)展情況。 B.建議該新團(tuán)隊(duì)成員參加自學(xué)培訓(xùn)課程。 C.允許該新團(tuán)隊(duì)成員單獨(dú)工作,但應(yīng)每日向項(xiàng)目經(jīng)理報(bào)告工作。 D.向該新團(tuán)隊(duì)成員提供項(xiàng)目管理計(jì)劃,并指定—名聯(lián)系人。 PMP答案解析:沒有經(jīng)驗(yàn)的團(tuán)隊(duì)成員要執(zhí)行一項(xiàng)困難任務(wù),可以通過培訓(xùn)、指導(dǎo)來(lái)提高技術(shù)技能。 PMP參考答案:A |