PMP考試練習題一: The total budget for a construction project is US$500 million. The management reserve is US$100 million. An unexpected event affects the project's progress. The project sponsor approves the use of US$50 million of the management resented to respond to the event. What is the revised cost baseline? A. US$400 million B. US$450 million C. US$500 million D. US$550 million 施工項目的總預算為5億美元。管理儲備為1億美元。一個意外事件影響了項目的進度。項目發(fā)起人批準使用5000萬美元的管理儲備來應對該事件。修訂后的成本基準是多少? A.4億美元 B.4.5億美元 C.5億美元 D.5.5億美元 PMP答案解析:成本基準不包括管理儲備,所以修訂前為4億美元,經(jīng)過批準,修訂后,管理儲備金進入新的成本基準,成為4.5億美元。 PMP參考答案:B PMP考試練習題二 A web development firm delivers a product to the client on time and 20% over the original budget. The client is currently soliciting bids for a new web project.What should the web development firm’s project manager do during the closure phase to enhance customer relations? A.Request requirements for the new web project B.Conduct a stakeholder analysis C.Meet with the client to review lessons learned D.Implement corrective actions of the budget controlling 一家網(wǎng)絡開發(fā)公司按時向客戶交付產(chǎn)品,但超出原始預算20%。客戶目前正在為一個新網(wǎng)絡項目投標。若要增強客戶關系,網(wǎng)絡開發(fā)公司的項目經(jīng)理在收尾階段應怎么做? A.索取新網(wǎng)絡項目的需求 B.進行干系人分析 C.與客戶開會,審查經(jīng)驗教訓 D.執(zhí)行預算控制的糾正措施 PMP答案解析:只有C是收尾階段需要做的 PMP參考答案:C |