PMP考試每天一練-2019年PMP考試練習題83
PMP考試練習題一: During a project's execution phase, a project manager determines that a criticalscheduled milestone may be missed, What should the project manager do? A. Perform a risk data quality assessment. B. Conduct a risk audit. C. Analyze the risk register. D. Review the risk response plan. 在項目的執行階段,項目經理確定了一個可能被錯過的關鍵計劃里程碑。項目經理應該怎么做? A.執行風險數據質量評估。 B.開展風險審計。 C.分析風險登記冊。 D.審查風險應對計劃。 PMP答案解析:風險應對計劃包含在規劃風險應對輸出和更新的風險登記冊中。 PMP參考答案:C PMP考試練習題二 A project manager’s construction project is on time, on scope and within budget. The project manager teams that a favorable weather forecast will allow for the implementation of critical path activities earlier than expected.What should the project manager do first? A. revise the schedule B. initiate perform integrated change control process C. check risk register D. follow the planned schedule 項目經理的施工項目符合時間、范圍以及預算。項目經理了解到有利的天氣預報將允許比預期提前執行關鍵路徑上的活動。項目經理首先該做什么? A.修訂進度計劃 B.開始執行整體變更控制過程 C.檢查風險登記冊 D.遵循計劃的進度計劃 PMP答案解析:積極風險,應該先查看風險登記冊是否有應對措施。 PMP參考答案:C |