PMP考試每天一練-2019年PMP考試練習題84
PMP考試練習題一: During a new system deployment, a company plans quality management. Which of the follow quality control activities should be included in this process? A.Audit the technical requirements for the system’s specifications B.Perform a process analysis to identify issues and plan preventive actions C.Produce a checklist to verify that a set of required steps were performed D.Examine whether the team is using best practices throughout the project 在一個新系統開發期間,公司制定質量管理計劃。下列哪一個質量控制應包含在這個過程? A.審核系統規格的技術要求 B.執行過程分析以識別問題并規劃預防措施 C.執行檢查表以核實項目按照規定的步驟和流程執行 D.檢查團隊是否在項目過程中執行良好的做法 PMP答案解析:公司制定質量管理計劃,說明正在進行規劃質量管理的過程。B、C、D都是在實施質量保證 PMP參考答案:A PMP考試練習題二 A company's model product has been selling well for many years, but the company now wants to rebrand it to meet developing market demands, During execution, a project team member points out that some older equipment and materials, amounting to US$50,000, need to be scrapped. This was not defined in the project management plan. Who should review and approve this cost threshold? A. Change control board (CCB) B. Functional management team C. Project manager D. Project management team 公司的模范產品已經暢銷多年,但該公司現在想更改品牌名稱,以滿足市場發展的需求。在執行過程中,項目團隊成員指出,需要報廢一些較舊的設備和材料,金額為50,000美元。這在項目管理計劃中未定義。誰應該審查和批準這個成本門檻? A.變更控制委員會(CCB) B.職能管理部門 C.項目經理 D.項目管理團隊 PMP答案解析:在項目管理計劃中末定義的成本項的變更,屬于成本基準的變更,通常由CCB來批準 PMP參考答案:A |