PMP考試每天一練-2019年PMP考試試題90
PMP考試試題一: Customer a implements a new system and awards the implementation phase to an external supplier B. A contract is signed with external supplier B. Supplier B would describe the contract as which of the following? A.Input to developing the project charter B.Output from developing the project charter C.Input to developing the project management plan D.Input to developing the schedule 客戶A實施一個新系統,并將實施階段授予外部供應商B來執行,并與供應商B簽訂合同。供應商B將會將該合同描述為下列哪一項? A.制定項目章程的輸入 B.制定項目章程的輸出 C.制定項目管理計劃的輸入 D.制定進度計劃的輸入 PMP答案解析:合同、協議是制定項目章程的輸入。 PMP參考答案:A PMP考試試題二 A critical project component is delivered by an external contractor and is evaluated for compliance with established technical requirements. What process is being performed? A. Plan Quality Performance B. Control Quality C. Assess Quality Risk D. Perform Quality Assurance 一個關鍵項目組件是由外部承包商交付的,并評估是否符合既定的技術要求。這正在執行哪個過程? A.制定質量績效計劃 B.控制質量 C.評估質量風險 D.實施質量保證 PMP答案解析:評估產品是否符合要求,是控制質量。 PMP參考答案:B |