PMP考試每天一練-2019年PMP考試試題91
PMP考試試題一: A project manager discovers that half of the project team members assigned to task B must first complete task A. What should the project manager use to adjust the schedule? A. Resource histogram B. Resource leveling C. Resource smoothing D. Resource optimization 項目經(jīng)理發(fā)現(xiàn)被分配到任務B的一半項目團隊成員必須首先完成任務A。項目經(jīng)理應該使用什么來調(diào)整進度計劃? A.資源直方圖 B.資源平衡 C.資源平滑 D.資源優(yōu)化 PMP答案解析:推薦 D答案,包括了資源平衡(用于關鍵路徑中的資源調(diào)整)與資源平滑(用于非關鍵路徑中的資源調(diào)整)。 PMP參考答案:D PMP考試試題二 Before developing a project charter, the project manager works with a consultant and subject matter experts to determine any constraints. Which of the following techniques did the project manager use? A.Lessons learned B.Historical information C.Strategic plan D.Expert judgment 制定項目章程之前,項目經(jīng)理與一名顧問和主題專家一起合作確定任何制約因素。項目經(jīng)理使用了下列哪一項技術? A.經(jīng)驗教訓 B.歷史信息 C.戰(zhàn)略計劃 D.專家判斷 PMP答案解析:和主題專家一起合作,這是專家判斷 PMP參考答案:D |