PMP考試每天一練-2019年PMP考試練習題106
PMP考試練習題一: A new project manager is assigned midway through a project. After conducting a project performance review, the project manager discovers that a supplier is unable to finish the work. At this stage, switching suppliers will carry considerable risk; however, not switching willresult in cost increases and schedule delays. What should the project manager do next? A . Analyze the impact and formulate a plan. B. Identify a new supplier as a replacement in case the issue recurs. C. Help the supplier to resolve the issue and finish the work. D. Ask management and the procurement department to resolve the issue. 項目經理接手了一個進展到一半的項目。在經過項目績效審查后,項目經理發(fā)現(xiàn)其中一個供應商并不具備完成工作的能力,但項目已進展到一半,更換供應商會帶來很大的風險。而不更換勢必會造成成本增加以及工期延后。項目經理應該如何應對? A.分析不同情況下所造成的影響,制定方案。 B.尋找新的供應商,在問題再次出現(xiàn)的時候直接替換。 C.協(xié)助供應商解決問題,輔助他們完成工作 D.交給采購部門去解決問題,并尋求管理層的幫助。 PMP答案解析:A答案包念了決策樹與EMV值的含義,為四個選項中最優(yōu)選項 PMP參考答案:A PMP考試練習題二 During project execution, the project team is unsure about their responsibilities. Which of the following should the project manager have prepared? 項目執(zhí)行期間,項目團隊不確定各自的責任。項目經理應制定下列哪一項? A.干系人分析 B.人員配備管理計劃 C.項目管理計劃 D.執(zhí)行,負責,咨詢和知情(RACI)矩陣 PMP答案解析:RACI矩陣是把人和事聯(lián)系起來 PMP參考答案:D |