PMP考試每天一練-2019年PMP考試練習題111
PMP考試練習題一: A project manager is ready to conduct the project kick-off meeting. What documents must be completed before the meeting? A. Project definition statement B. Project statement of work (SOW) C. Project charter D. Stakeholder management plan 項目經(jīng)理準備召開項目啟動大會。召開會議之前必須完成哪份文件? A.項目定義說明書 B.項目工作說明書(SOW) C.項目章程 D.干系人管理計劃 PMP答案解析:啟動大會在規(guī)劃結束,執(zhí)行開始之前召開,完成干系人管理計劃代表規(guī)劃結束。 PMP參考答案:D PMP考試練習題二 A potential client submits a multiyear project’s request for proposal to the project manager. Before presenting any documents, the project manager speaks with the client and discusses the information received. Next, the project manager discusses the information internally.The project manager is doing which of the following? A.Develop the project charter B.Define the high-level scope C.Identify the high-level risks D.Perform a key stakeholder analysis 一個潛在客戶向項目經(jīng)理提交了一個為期多年的項目建議邀請書。在提交任何文件之前,項目經(jīng)理與客戶聯(lián)系,并討論接收到的信息。接下來,項目經(jīng)理在內(nèi)部討論這些信息。項目經(jīng)理正在從事下列哪一項工作? A.制定項目章程 B.定義高層次范圍 C.識別高層次風險 D.執(zhí)行關鍵干系人分析 PMP答案解析:客戶提交了建議邀請書(采購文件),在收到客戶的信息,開始探討信息。應該是根據(jù)客戶的信息,在定義大致的范圍,然后再根據(jù)范圍,識別高層次風險。 PMP參考答案:B |